Halmtorvet 20-22

20

Technical and environmental details

Environmental considerations On 8 October 2024, Rambøll carried out an environmental screening of the Property to assess whether plans to redevelop the Property would be required to factor in any environmental considerations.

The resulting Rambøll screening report identifies findings of two hazardous materials in the construction:

1. Asbestos was detected in the windbreaker panel behind the font building’s turquoise facade panels. As the facade was mounted via the windbreaker panel, special precautions are believed to be called for if and when removing facade panels. 2. PCB was detected in the wall paint in multiple stairwells as well as on the building front facing the inner courtyard. Special precautions are called for if and when removing the paint. State of technical installations Rambøll has carried out a high-level assessment of the Property’s technical installations. The report concludes that a full replacement is to take place of all piping (both drinking water and heating), ventilation and cooling (both plant and ducts), CTS and ABA.

The heating plant itself is district heating and does not require replacement. There is also an option to connect the Property to district cooling.

Made with FlippingBook flipbook maker