Project Grid
Indicative process timeline (assuming positive feedback from soft testing)
December
January
February
March
November
October
Week
4041 424344454647484950 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13
Preparation
Kick-off meeting
Collection of documents and preparation of VDR
Approval of investor long-list
Soft testing, preparation of investor short-list and approval
Preparation of sales material and approval
Marketing
Distribution and negotiation of NDAs
Distribution of sales material (subject to signing of NDA)
Investor dialogue, investor presentations and property tours
Deadline for indicative bids
Evaluation of indicative bids and selection of preferred investor
Negotiation of HoT and granting of exclusivity
Due diligence and negotiation
Due diligence
Negotiation of transaction documents
Colliers| Proposal for advisory services | 19
Signing of transaction documents
Closing (TBD)
Note:
= Process milestone
= Danish holiday period
Made with FlippingBook - Online magazine maker